CappKind quantity surveying risk specialists worked with the NGN – Redcar Hydrogen Community commercial team to establish the risk objectives. These included,
1) Understanding the outturn risk exposure of the enabling works investment, if the government made an ‘early, mid or late’ decision on the full investment proposal.
2) Profiling the risk envelop across time to understand when critical investment decisions needed to be taken and what the associated risk of these decision was.
CappKind used @Risk, Quantitative Risk Analysis software, to develop a risk model that incorporated the circa 75 key risks. A three-point estimate of each risk and a probability were assessed. This input risk data was processed through a Monte Carlo risk simulation technique – effectively simulating the delivery of the enabling works through 10,000 iterations. This enabled a high-quality outturn risk envelop to be charted for each scenario.
In addition, sensitivity analysis and ‘tornado charts’ provided information on the relative significance of each risk input to the overall output risk envelope.
Finally, P10, P50 and P90 risk positions were plotted over a cashflow forecast and critical decision dates were overlaid on these profiles.
The work provided two key outputs,
1) The detailed modelling sheets and a full data suite.
2) A board-level presentation enabling data driven decision making.
Key benefits
AMP6 capital programme commercial assurance